The Lincoln Park Tower Riser Project is a major building-wide upgrade focused on replacing the aging plumbing system to ensure long-term reliability and improved service for residents. The work includes new hot and cold water supply lines, waste piping, shower valves, and updated in-unit fixtures such as tub/shower units, bathroom sinks, medicine cabinets, and kitchen faucets. Construction will be completed in three phases to minimize disruption: Phase 1 covers the north and south low-rise wings, Phase 2 covers the main tower (each with sub-phases), and Phase 3 addresses the machanical room and common areas. This comprehensive approach addresses onging plumbing issues, reduces maintenance needs, and modernizes apartment bathrooms and kitchens as part of a durable, long-term solution.

WHY REPLACE THE WATER RISER SYSTEM?
Due to age, current condition of the water risers, and the volume of work orders associated with the plumbing system, it was determined that a complete overhaul of the water riser system would be an appropriate action for a long-term solution. Because the riser replacement work involves removing of the existing fixtures and appliances, it was further determined that the new fixures and new shower surrounds would be replaced at the same time.

WHAT TO KNOW
  • LPT was built in 1968 and contains 199 units.

  • Work is being done in three phases:
    • Phase 1: North and south low-rise wings (phases 1A and 1B)
    • Phase 2: Main tower
    • Phase 3: Mechanical room and common area work

  • The project scopes involve replacing:
    • Hot & cold water supply lines
    • waste lines
    • Shower valves
    • Bathroom tub/shower
    • Bathroom sink
    • Bathroom medicine cabinets
    • Kitchen faucets

  • Residents will be relocated as part of a coordinated relocation plan during each phase.

  • Informational resident meetings have been held on a regular basis since late 2025.

  • UPDATES
    Regular updates will be posted in this section throughout the entirety of the project.

    FREQUENTLY ASKED QUESTIONS (FAQ’s)



    RELOCATION PACKET


    This packet includes a comprehensive checklist intended to help LPT residents prepare for relocation.

    HOTEL RELOCATION—WHAT TO EXPECT


    For LPT residents who will temporarily reside in a pre-arranged hotel, this document describes your hotel room, food and meals, housekeeping, on-site amenities and services and other important information.

    1BR UNIT PLANS


    STUDIO UNIT PLANS



    FLOOR PLANS

    COMING UP
    A schedule of work to be done

    PHOTOS
    WHA will maintain a photo library chronicling this project from resident meeting up to and including project completion